Intel Corporation is currently constructing two leading-edge semiconductor fabrication facilities near New Albany in Licking County; however, the company has intentionally moderated construction pacing to align capital spending with customer foundry commitments. Under schedules disclosed in 2025, Intel plans to complete construction of the first module in 2030 with initial commercial operations between 2030 and 2031, while the second module is scheduled for completion in 2031 and operations in 2032. The site currently operates as an active, multi-year industrial construction and public utility infrastructure corridor rather than a commercial chip manufacturing campus.
- Core Project Status: Intel has moderated the pace of its Ohio One semiconductor campus in New Albany, scheduling initial module completion for 2030 and volume manufacturing operations for 2030–2031, reflecting corporate capital discipline and customer foundry commitments.
- Who Is Affected: Central Ohio construction trade unions, municipal taxpayers in New Albany and Licking County, local school districts managing 30-year Community Reinvestment Area (CRA) property tax abatements, and regional supply chain vendors.
- Verified Status by Progress Stage:
- Projected / Long-Term: $100B 8-fab full buildout vision; 3,000 permanent fab operator positions at full operations.
- Approved / Enacted: U.S. Department of Commerce restructured $8.9B common-stock and milestone agreement; 30-year New Albany CRA property tax abatement.
- Underway / Active: $28B+ private capital budget for the initial two fabs; $123M recognized in capital grants for Ohio in 2025; active construction trades on site.
- Completed & Operational: $90M ODOT highway and SR 161 modernizations; 4 miles of municipal water transmission piping; 2-million-gallon elevated water storage tank.

1. The Current Timeline Replaces the Original Launch Narrative
Intel announced its Ohio One project in 2022, breaking ground later that year in the New Albany International Business Park. The initial phase expanded from an announced $20 billion to more than $28 billion for two manufacturing facilities. While public announcements frequently referenced an aspirational $100 billion mega-complex spanning eight fabs, that figure represents a potential long-term scenario rather than capital formally committed to completed factories.
In February 2025, Intel Corporation disclosed that construction of Module 1 was projected for completion in 2030, with volume operations initiating between 2030 and 2031. Module 2 was scheduled for completion in 2031 and operations in 2032. In July 2025, Intel leadership announced that the company was further moderating the construction pace in Ohio to align capital expenditures with customer demand and market wins. Intel’s official annual report reiterates that capital allocation for Ohio remains disciplined to match verified commercial capacity needs.
These disclosures clarify key empirical boundaries: Ohio One is not producing commercial silicon chips today; projected long-term manufacturing headcounts reflect future operational targets rather than active payroll; and the eight-fab concept remains an uncommitted option. A rigorous progress assessment requires separating earthwork, building shell erection, utility connection, extreme ultraviolet (EUV) tool installation, process qualification, and commercial yield ramp.
| Project Dimension | Initial Announcement | Status Stage (Phân định tiến độ) | Verified 2026 Status | Empirical Limitation |
|---|---|---|---|---|
| Fab Construction Scope | Two leading-edge semiconductor fabs | Underway / Active | Under active construction; structural pace adjusted to customer demand | No commercial chip fabrication in Ohio prior to 2030 |
| Initial Phase Capital | $20 Billion expanding to $28+ Billion | Projected / Corporate Target | Stated private capital budget for first two fabs | Actual capital deployment calibrated to corporate cash flow and market demand |
| Full Campus Buildout | Up to $100 Billion across eight fabs | Projected / Long-Term Vision | Long-term hypothetical development concept | Not a legally binding construction commitment or invested sum |
| Workforce Headcount | 3,000 permanent & 7,000 construction jobs | Underway vs Operational Target | Estimated targets for full operational phase | Current workforce consists of active construction trades, not permanent fab operators |
| Federal CHIPS Support | Nationwide direct grant allocations | Approved / Restructured Equity | Restructured into $8.9B federal common-stock and milestone agreement | Multi-state award; Ohio receives milestone-tied portions ($123M recognized in 2025) |
| Highway Modernization | $90M regional freight improvements | Completed & Operational | ODOT highway and SR 161 widening projects completed and in service | Public road contracts independently completed by ODOT |
| Municipal Water Infrastructure | Dedicated industrial water supply | Completed & Operational | 4 miles of water main, 6 MGD lift station, and 2M-gal tank operational | Infrastructure readiness completed by City of New Albany |
2. Federal Support Restructured into Equity and Milestone Agreements
In November 2024, the U.S. Department of Commerce finalized a multi-state CHIPS and Science Act award of up to $7.865 billion covering Intel facilities across Arizona, New Mexico, Ohio, and Oregon, with disbursements tied strictly to verified construction, technology qualification, and production milestones. This represented a national multi-facility award, rather than a single grant check to Licking County.
The federal funding architecture underwent a major structural revision in August 2025. Intel announced an agreement under which the federal government would execute an $8.9 billion common-stock investment, funded by $5.7 billion in previously allocated but unpaid CHIPS grants and $3.2 billion from the Secure Enclave defense initiative. Intel noted it had received $2.2 billion in direct CHIPS grants at that stage. The Department of Commerce’s fiscal year financial disclosures document this warrant and stock framework, which amends earlier grant covenants.
Intel’s annual financial reporting provides a verified Ohio accounting datapoint: the company recognized $123 million in capital grants specifically related to its two Ohio fabs during 2025. This localized figure should not be conflated with total public road spending, state tax exemptions, company-wide federal equity investments, or total private capital outlays.
3. Highway Infrastructure and Superload Logistics
Public transportation enhancements surrounding the future campus are moving forward under state and municipal contracts. The City of New Albany’s Silicon Heartland portal documents an Ohio Department of Transportation (ODOT) commitment of $90 million dedicated to regional highway and roadway modernization, centered on primary corridors across Delaware, Franklin, and Licking counties. Active projects include grade separations, widening segments of State Route 161, and local intersection redesigns with independent construction contracts and phased completion schedules.
Heavy industrial freight deliveries have traveled along designated heavy-haul routes from an Ohio River barge dock at Manchester in Adams County north to New Albany. Documented logistics notices show specific oversized loads: municipal updates for convoys 35 and 36 recorded a 162-foot pipe-rack module weighing 333,176 pounds and structural steel components weighing 93,500 pounds. These heavy transport operations reflect significant logistical coordination; however, each superload is planned individually, carrying specific structural steel, transformers, or process piping rather than uniform machinery.

4. Water Infrastructure Engineering and Environmental Permitting
New Albany operates as a contract utility community: the city finances, constructs, and maintains local water pipes, booster pumps, and storage tanks, while the City of Columbus supplies treated municipal water and processes wastewater under intergovernmental master agreements. New Albany’s municipal budget documents confirm the completion of four miles of large-diameter water transmission piping, a regional sewage lift station designed to discharge up to 6 million gallons per day (MGD), and a completed 2-million-gallon elevated water storage tank adjacent to the technology park.
These engineered municipal capacities represent infrastructure readiness rather than active factory consumption. Semiconductor manufacturing requires high volumes of ultrapure water (UPW) and produces regulated industrial process wastewater. While advanced chipmakers aim for ambitious water reclamation targets, actual daily consumption rates, chemical pretreatment efficiency, and recycling percentages can only be verified from metered discharge monitoring reports once cleanroom production is operational.
Environmental governance is anchored by the Ohio Environmental Protection Agency (Ohio EPA), which issued an air Permit-to-Install (PTI) authorizing equipment installation and phased operation for up to four manufacturing modules across two building shells, subject to emissions controls, continuous scrubbers, and subsequent Title V operating reviews. Construction activities also operate under state stormwater pollution prevention plans and wetland mitigation permits.
5. Electrical Grid Interconnection and Reliability Architecture
Supplying continuous, high-reliability power to an advanced semiconductor fabrication complex requires extensive transmission engineering. Regional grid planning coordinated through American Electric Power (AEP Ohio) and regional transmission operator PJM Interconnection involves multi-million-dollar substation investments, redundant transmission circuits, and upgraded high-voltage lines across Central Ohio.
For rigorous public accountability, large-scale utility infrastructure claims must be verified against formal case dockets filed with the Public Utilities Commission of Ohio (PUCO) and the Ohio Power Siting Board (OPSB). Capital expenditures, customer rate allocations, and in-service dates are subject to regulatory filings that differentiate dedicated customer interconnection facilities from general regional grid modernization.
6. Workforce Pipelines, Municipal Agreements, and Community Fiscal Impacts
Public announcements project that the Ohio One campus could support 3,000 permanent advanced manufacturing positions and up to 7,000 construction jobs at peak activity. Intel has supported technical education programs across Ohio universities, community colleges, and vocational schools, and specialized technicians have completed training rotations at operating Intel facilities in Oregon and Arizona. However, long-term employment counts depend on production commissioning timelines and actual fabrication volumes.
The regional supplier ecosystem is similarly evolving at a disciplined pace. While original development concepts anticipated attracting dozens of Tier-1 and Tier-2 suppliers to Licking and surrounding counties, verified vendor commitments require tracking individual commercial land purchases, municipal zoning approvals, and facility groundbreakings.
Local public services and municipal budgets are shaped by formal development agreements. Under a 30-year Community Reinvestment Area (CRA) property tax abatement approved by the New Albany City Council in 2022, property taxes on structural improvements are abated, with negotiated revenue-sharing and income-tax withholding mechanisms designed to support local school districts and municipal services. The net fiscal impact of these agreements will unfold over decades, calibrated to factory completion schedules and actual payroll generation.

7. A Public Accountability Framework for Megaproject Tracking
To provide transparent monitoring of large-scale industrial megaprojects, public reporting should measure progress against six empirical benchmarks:
- Construction Milestones: Module-by-module structural completion, utility hookup dates, cleanroom certification, and formal reasons for schedule revisions.
- Public Financing Disbursements: Authorized federal, state, and local incentives, verified disbursement triggers, milestone compliance, and statutory clawback provisions.
- Verified Headcount: Direct permanent payroll distinguished from transient construction labor, wage brackets, and local Ohio residency percentages.
- Water and Environmental Performance: Permitted capacity compared to actual metered consumption, industrial wastewater pretreatment compliance, and discharge monitoring reports.
- Electric Grid Integration: Verified utility rate cases, regulatory filings with PUCO/OPSB, peak demand curves, and carbon accounting standards.
- Local Municipal Capacity: Traffic volume counts, emergency service response times, public school funding distributions, and municipal debt obligations.
Intel Ohio One remains a historic industrial endeavor that is actively reshaping Central Ohio’s built environment. However, its factual status in 2026 is distinct from a fully realized manufacturing center: construction has been intentionally paced, commercial production is scheduled for the turn of the decade, federal financing has adapted, and community economic multipliers remain forward-looking forecasts. Rigorous, source-verified tracking offers the most dependable guide for residents, workers, civic planners, and public institutions.
Editorial Record & Methodology Revision (October 2026)
State News Now updated this report to align all figures strictly with primary SEC filings, audited municipal records, and regulatory permits. Earlier reporting that assumed immediate commercial manufacturing timelines, dedicated 765-kV utility substation assets, unverified water recycling percentages, and unconfirmed supplier counts has been superseded by verified public filings from Intel Corporation, the U.S. Department of Commerce, Ohio EPA, and the City of New Albany.
8. Primary Official and Company Sources
- Intel Corporation: February 2025 Ohio One Construction Schedule Update
- Intel Corporation: July 2025 Executive Strategic Capital Allocation Disclosures
- Intel Corporation 2025 Annual Report: Ohio Pace, Capital Grants, and Asset Disclosures
- U.S. Department of Commerce: November 2024 Intel CHIPS Award Documentation
- U.S. Department of Commerce: FY2025 Financial Report & Common-Stock Agreement
- City of New Albany: Silicon Heartland Construction & Infrastructure Portal
- City of New Albany: Superload Dimensions, Route Notices, and Weights
- City of New Albany: Water, Sewer, Road, and Technology Park Capital Budgets
- Ohio EPA & City of New Albany: Industrial Permit Summary
- City of New Albany: Intel Community Reinvestment Area (CRA) Agreement
Recommended In-Depth Reads
- Kentucky’s Glendale Megacampus: Inside Ford’s Energy Storage Shift — How shifting market demand and grid battery storage reconfigure state-backed industrial projects.
- Illinois Hydrogen and Freight in 2026: What Is Funded, Proposed, and Operational — An analysis of Midwestern freight decarbonization, federal hydrogen hub awards, and public logistics infrastructure.




